Casa Nueva Project Schedule

0201 CS Baseline 20021106


Project Start Date: Wed 11/06/02
Project Finish Date: Wed 05/14/03

ID
Task_Name
DurationStart_Date Finish_Date Predecessors
1
Building
136 dWed 11/06/02 Wed 05/14/03 
2
Structural
15 dWed 11/06/02 Tue 11/26/02 
3
Gridlines A-C/1-6
15 dWed 11/06/02 Tue 11/26/02 
4
A-C/1-6 Stl Flr Bms
5 dWed 11/06/02 Tue 11/12/02 
5
A-C/1-6 Brc Fms
10 dWed 11/06/02 Tue 11/19/024SS
6
A-C/1-6 Bld Rf Bms
9 dWed 11/13/02 Mon 11/25/025SS+5 d
7
A-C/1-6 Set Rf Bms
1 dTue 11/26/02 Tue 11/26/026
8
A-C/1-6 Roll Joists
2 dWed 11/13/02 Thu 11/14/024
9
A-C/1-6 Blk Joists
5 dFri 11/15/02 Thu 11/21/028
10
A-C/1-6 Ply Deck
3 dFri 11/22/02 Tue 11/26/029
11
Gridlines A-F/6-8
10 dWed 11/06/02 Tue 11/19/02 
12
A-F/6-8 Blk Joists
4 dWed 11/06/02 Mon 11/11/02 
13
A-F/6-8 Ply Deck
3 dTue 11/12/02 Thu 11/14/0212
14
A-F/6-8 Bld Rf Bms
9 dWed 11/06/02 Mon 11/18/02 
15
A-F/6-8 Set Rf Bms
1 dTue 11/19/02 Tue 11/19/0214
16
Roof
35 dWed 11/27/02 Tue 01/14/03 
17
Set Roof Joists
3 dWed 11/27/02 Fri 11/29/027,15
18
Blk Rf Joists/Ply Deck
8 dMon 12/02/02 Wed 12/11/0217
19
Rf Curbs/Pads/Flshg
5 dThu 12/12/02 Wed 12/18/0218
20
Built-Up Roofing
10 dThu 12/19/02 Wed 01/01/0319
21
Set Equipment
5 dWed 01/08/03 Tue 01/14/0320,41
22
1st Floor
95 dWed 11/27/02 Tue 04/08/03 
23
Interior
95 dWed 11/27/02 Tue 04/08/03 
24
Int Wall Framing
20 dWed 11/27/02 Tue 12/24/0210,13
25
MEP Rough-In
20 dWed 12/25/02 Tue 01/21/0324
26
Gyp Bd Side 1
7 dWed 12/25/02 Thu 01/02/0324
27
Insulate
3 dFri 01/17/03 Tue 01/21/0325FF,26
28
Gyp Bd Side 2/Dr Fms
5 dWed 01/22/03 Tue 01/28/0327
29
Tape/Texture
10 dWed 01/29/03 Tue 02/11/0328
30
Bath Cer Flr Tile
5 dWed 02/12/03 Tue 02/18/0329
31
Int Paint
10 dWed 02/12/03 Tue 02/25/0329
32
Toil Part/Acc
5 dWed 02/26/03 Tue 03/04/0330,31
33
Cabs/C-Tops
10 dWed 02/26/03 Tue 03/11/0331
34
MEP Finishes
20 dWed 02/26/03 Tue 03/25/0331
35
T-Bar Ceilings
10 dWed 02/26/03 Tue 03/11/0331
36
Drs/Fms/Hdwe
20 dWed 02/26/03 Tue 03/25/0331
37
Mouldings
10 dWed 02/26/03 Tue 03/11/0331
38
Flooring
10 dWed 03/26/03 Tue 04/08/03 33,34,35,36,37
39
Exterior
60 dWed 11/27/02 Tue 02/18/03 
40
Ext Wall Framing
10 dWed 11/27/02 Tue 12/10/0210,13
41
Lath Exterior
10 dWed 12/25/02 Tue 01/07/0324,40
42
Windows
10 dWed 01/08/03 Tue 01/21/0341
43
Plaster
10 dWed 01/22/03 Tue 02/04/0321,42
44
Ext Paint
5 dWed 02/05/03 Tue 02/11/0343
45
Ext Finishes/Fixtures
5 dWed 02/12/03 Tue 02/18/0344
46
2nd Floor
100 dThu 12/12/02 Wed 04/30/03 
47
Interior
100 dThu 12/12/02 Wed 04/30/03 
48
Int Wall Framing
20 dThu 12/12/02 Wed 01/08/0318
49
MEP Rough-In
20 dThu 01/09/03 Wed 02/05/0348
50
Gyp Bd Side 1
7 dThu 01/09/03 Fri 01/17/0348
51
Insulate
3 dMon 02/03/03 Wed 02/05/0349FF,50
52
Gyp Bd Side 2/Dr Fms
5 dThu 02/06/03 Wed 02/12/0351
53
Gypcrete
5 dThu 02/13/03 Wed 02/19/0352
54
Tape/Texture
10 dThu 02/20/03 Wed 03/05/0353
55
Bath Cer Flr Tile
5 dThu 03/06/03 Wed 03/12/0354
56
Int Paint
10 dThu 03/06/03 Wed 03/19/0354
57
Toil Part/Acc
5 dThu 03/20/03 Wed 03/26/0355,56
58
Cabs/C-Tops
10 dThu 03/20/03 Wed 04/02/0356
59
MEP Finishes
20 dThu 03/20/03 Wed 04/16/0356
60
T-Bar Ceilings
10 dThu 03/20/03 Wed 04/02/0356
61
Drs/Fms/Hdwe
20 dThu 03/20/03 Wed 04/16/0356
62
Mouldings
10 dThu 03/20/03 Wed 04/02/0356
63
Flooring
10 dThu 04/17/03 Wed 04/30/03 58,59,60,61,62
64
Exterior
60 dThu 12/12/02 Wed 03/05/03 
65
Ext Wall Frmg
10 dThu 12/12/02 Wed 12/25/0218
66
Lath Exterior
10 dThu 01/09/03 Wed 01/22/0348,65
67
Windows
10 dThu 01/23/03 Wed 02/05/0366
68
Plaster
10 dThu 02/06/03 Wed 02/19/0367
69
Ext Paint
5 dThu 02/20/03 Wed 02/26/0368
70
Ext Finishes/Fixtures
5 dThu 02/27/03 Wed 03/05/0369
71
Bldg Punch
10 dThu 05/01/03 Wed 05/14/03 38,32,63,45,70
72
Sitework
121 dWed 11/06/02 Wed 04/23/03 
73
North Lot
15 dWed 11/20/02 Tue 12/10/02 
74
Demo/Fine Grade
2 dWed 11/20/02 Thu 11/21/0215
75
Utilities
3 dFri 11/22/02 Tue 11/26/0274
76
Irrig
3 dFri 11/22/02 Tue 11/26/0274
77
C/G/S
5 dWed 11/27/02 Tue 12/03/0275
78
AC/Grass Pave
4 dWed 12/04/02 Mon 12/09/0277
79
Misc Site Furn
5 dWed 12/04/02 Tue 12/10/0277
80
Planting
5 dWed 12/04/02 Tue 12/10/0276,77
81
Courtyard
98 dWed 11/06/02 Fri 03/21/03 
82
Block Walls
8 dWed 11/06/02 Fri 11/15/02 
83
Fine Grading
2 dThu 02/20/03 Fri 02/21/0382,43,68
84
Utilities
5 dMon 02/24/03 Fri 02/28/0383
85
Irrigation
7 dMon 02/24/03 Tue 03/04/0383
86
Cisterns
5 dMon 03/03/03 Fri 03/07/0384
87
Flatwork
10 dMon 03/03/03 Fri 03/14/0384
88
Misc Site Furn
5 dMon 03/17/03 Fri 03/21/0386,87
89
Planting
5 dMon 03/17/03 Fri 03/21/0385,87
90
SouthEast Lot
20 dThu 02/20/03 Wed 03/19/03 
91
Demo/Fine Grade
3 dThu 02/20/03 Mon 02/24/0343,68
92
Utilities
2 dTue 02/25/03 Wed 02/26/0391
93
Irrig
3 dTue 02/25/03 Thu 02/27/0391
94
C/G/S
5 dThu 02/27/03 Wed 03/05/0392
95
AC/Grass Pave
5 dThu 03/06/03 Wed 03/12/0394
96
Misc Site Furn
2 dThu 03/06/03 Fri 03/07/0394
97
Planting
5 dThu 03/13/03 Wed 03/19/0393,95
98
SouthWest Lot
40 dWed 11/06/02 Tue 12/31/02 
99
Haul-off Spoils
3 dWed 11/06/02 Fri 11/08/02 
100
Demo/Fine Grade
3 dMon 11/11/02 Wed 11/13/0299
101
Utilities
7 dThu 11/14/02 Fri 11/22/02100
102
Irrig
5 dThu 11/14/02 Wed 11/20/02100
103
Walls/Stairs
10 dMon 11/25/02 Fri 12/06/02101
104
C/G/S
10 dMon 12/09/02 Fri 12/20/02103
105
AC/Grass Pave
2 dMon 12/23/02 Tue 12/24/02104
106
Misc Site Furn
5 dMon 12/23/02 Fri 12/27/02104
107
Planting
5 dWed 12/25/02 Tue 12/31/02102,105
108
Shade Structure
35 dThu 02/20/03 Wed 04/09/03 
109
Drill Holes
5 dThu 02/20/03 Wed 02/26/0343,68
110
Set Posts
5 dThu 02/27/03 Wed 03/05/03109
111
Hardware
10 dThu 03/06/03 Wed 03/19/03110
112
Trellises
10 dThu 03/06/03 Wed 03/19/03110
113
Paint Poles
5 dThu 03/06/03 Wed 03/12/03110
114
Paint Hdwe/Trellises
5 dThu 03/20/03 Wed 03/26/03111,112
115
Fabric/Mesh
10 dThu 03/27/03 Wed 04/09/03113,114
116
Site Punchlist
10 dThu 04/10/03 Wed 04/23/03 115,78,79,80,88,89,96,97,106,107
117
Completion
0 dWed 11/06/02 Wed 11/06/02