Casa Nueva Project Schedule0201 CS Baseline 20021106
|
| ID | Task_Name |
Duration | Start_Date | Finish_Date | Predecessors |
|---|---|---|---|---|---|
| 1 | Building |
136 d | Wed 11/06/02 | Wed 05/14/03 | |
| 2 | Structural |
15 d | Wed 11/06/02 | Tue 11/26/02 | |
| 3 | Gridlines A-C/1-6 |
15 d | Wed 11/06/02 | Tue 11/26/02 | |
| 4 | A-C/1-6 Stl Flr Bms |
5 d | Wed 11/06/02 | Tue 11/12/02 | |
| 5 | A-C/1-6 Brc Fms |
10 d | Wed 11/06/02 | Tue 11/19/02 | 4SS |
| 6 | A-C/1-6 Bld Rf Bms |
9 d | Wed 11/13/02 | Mon 11/25/02 | 5SS+5 d |
| 7 | A-C/1-6 Set Rf Bms |
1 d | Tue 11/26/02 | Tue 11/26/02 | 6 |
| 8 | A-C/1-6 Roll Joists |
2 d | Wed 11/13/02 | Thu 11/14/02 | 4 |
| 9 | A-C/1-6 Blk Joists |
5 d | Fri 11/15/02 | Thu 11/21/02 | 8 |
| 10 | A-C/1-6 Ply Deck |
3 d | Fri 11/22/02 | Tue 11/26/02 | 9 |
| 11 | Gridlines A-F/6-8 |
10 d | Wed 11/06/02 | Tue 11/19/02 | |
| 12 | A-F/6-8 Blk Joists |
4 d | Wed 11/06/02 | Mon 11/11/02 | |
| 13 | A-F/6-8 Ply Deck |
3 d | Tue 11/12/02 | Thu 11/14/02 | 12 |
| 14 | A-F/6-8 Bld Rf Bms |
9 d | Wed 11/06/02 | Mon 11/18/02 | |
| 15 | A-F/6-8 Set Rf Bms |
1 d | Tue 11/19/02 | Tue 11/19/02 | 14 |
| 16 | Roof |
35 d | Wed 11/27/02 | Tue 01/14/03 | |
| 17 | Set Roof Joists |
3 d | Wed 11/27/02 | Fri 11/29/02 | 7,15 |
| 18 | Blk Rf Joists/Ply Deck |
8 d | Mon 12/02/02 | Wed 12/11/02 | 17 |
| 19 | Rf Curbs/Pads/Flshg |
5 d | Thu 12/12/02 | Wed 12/18/02 | 18 |
| 20 | Built-Up Roofing |
10 d | Thu 12/19/02 | Wed 01/01/03 | 19 |
| 21 | Set Equipment |
5 d | Wed 01/08/03 | Tue 01/14/03 | 20,41 |
| 22 | 1st Floor |
95 d | Wed 11/27/02 | Tue 04/08/03 | |
| 23 | Interior |
95 d | Wed 11/27/02 | Tue 04/08/03 | |
| 24 | Int Wall Framing |
20 d | Wed 11/27/02 | Tue 12/24/02 | 10,13 |
| 25 | MEP Rough-In |
20 d | Wed 12/25/02 | Tue 01/21/03 | 24 |
| 26 | Gyp Bd Side 1 |
7 d | Wed 12/25/02 | Thu 01/02/03 | 24 |
| 27 | Insulate |
3 d | Fri 01/17/03 | Tue 01/21/03 | 25FF,26 |
| 28 | Gyp Bd Side 2/Dr Fms |
5 d | Wed 01/22/03 | Tue 01/28/03 | 27 |
| 29 | Tape/Texture |
10 d | Wed 01/29/03 | Tue 02/11/03 | 28 |
| 30 | Bath Cer Flr Tile |
5 d | Wed 02/12/03 | Tue 02/18/03 | 29 |
| 31 | Int Paint |
10 d | Wed 02/12/03 | Tue 02/25/03 | 29 |
| 32 | Toil Part/Acc |
5 d | Wed 02/26/03 | Tue 03/04/03 | 30,31 |
| 33 | Cabs/C-Tops |
10 d | Wed 02/26/03 | Tue 03/11/03 | 31 |
| 34 | MEP Finishes |
20 d | Wed 02/26/03 | Tue 03/25/03 | 31 |
| 35 | T-Bar Ceilings |
10 d | Wed 02/26/03 | Tue 03/11/03 | 31 |
| 36 | Drs/Fms/Hdwe |
20 d | Wed 02/26/03 | Tue 03/25/03 | 31 |
| 37 | Mouldings |
10 d | Wed 02/26/03 | Tue 03/11/03 | 31 |
| 38 | Flooring |
10 d | Wed 03/26/03 | Tue 04/08/03 | 33,34,35,36,37 |
| 39 | Exterior |
60 d | Wed 11/27/02 | Tue 02/18/03 | |
| 40 | Ext Wall Framing |
10 d | Wed 11/27/02 | Tue 12/10/02 | 10,13 |
| 41 | Lath Exterior |
10 d | Wed 12/25/02 | Tue 01/07/03 | 24,40 |
| 42 | Windows |
10 d | Wed 01/08/03 | Tue 01/21/03 | 41 |
| 43 | Plaster |
10 d | Wed 01/22/03 | Tue 02/04/03 | 21,42 |
| 44 | Ext Paint |
5 d | Wed 02/05/03 | Tue 02/11/03 | 43 |
| 45 | Ext Finishes/Fixtures |
5 d | Wed 02/12/03 | Tue 02/18/03 | 44 |
| 46 | 2nd Floor |
100 d | Thu 12/12/02 | Wed 04/30/03 | |
| 47 | Interior |
100 d | Thu 12/12/02 | Wed 04/30/03 | |
| 48 | Int Wall Framing |
20 d | Thu 12/12/02 | Wed 01/08/03 | 18 |
| 49 | MEP Rough-In |
20 d | Thu 01/09/03 | Wed 02/05/03 | 48 |
| 50 | Gyp Bd Side 1 |
7 d | Thu 01/09/03 | Fri 01/17/03 | 48 |
| 51 | Insulate |
3 d | Mon 02/03/03 | Wed 02/05/03 | 49FF,50 |
| 52 | Gyp Bd Side 2/Dr Fms |
5 d | Thu 02/06/03 | Wed 02/12/03 | 51 |
| 53 | Gypcrete |
5 d | Thu 02/13/03 | Wed 02/19/03 | 52 |
| 54 | Tape/Texture |
10 d | Thu 02/20/03 | Wed 03/05/03 | 53 |
| 55 | Bath Cer Flr Tile |
5 d | Thu 03/06/03 | Wed 03/12/03 | 54 |
| 56 | Int Paint |
10 d | Thu 03/06/03 | Wed 03/19/03 | 54 |
| 57 | Toil Part/Acc |
5 d | Thu 03/20/03 | Wed 03/26/03 | 55,56 |
| 58 | Cabs/C-Tops |
10 d | Thu 03/20/03 | Wed 04/02/03 | 56 |
| 59 | MEP Finishes |
20 d | Thu 03/20/03 | Wed 04/16/03 | 56 |
| 60 | T-Bar Ceilings |
10 d | Thu 03/20/03 | Wed 04/02/03 | 56 |
| 61 | Drs/Fms/Hdwe |
20 d | Thu 03/20/03 | Wed 04/16/03 | 56 |
| 62 | Mouldings |
10 d | Thu 03/20/03 | Wed 04/02/03 | 56 |
| 63 | Flooring |
10 d | Thu 04/17/03 | Wed 04/30/03 | 58,59,60,61,62 |
| 64 | Exterior |
60 d | Thu 12/12/02 | Wed 03/05/03 | |
| 65 | Ext Wall Frmg |
10 d | Thu 12/12/02 | Wed 12/25/02 | 18 |
| 66 | Lath Exterior |
10 d | Thu 01/09/03 | Wed 01/22/03 | 48,65 |
| 67 | Windows |
10 d | Thu 01/23/03 | Wed 02/05/03 | 66 |
| 68 | Plaster |
10 d | Thu 02/06/03 | Wed 02/19/03 | 67 |
| 69 | Ext Paint |
5 d | Thu 02/20/03 | Wed 02/26/03 | 68 |
| 70 | Ext Finishes/Fixtures |
5 d | Thu 02/27/03 | Wed 03/05/03 | 69 |
| 71 | Bldg Punch |
10 d | Thu 05/01/03 | Wed 05/14/03 | 38,32,63,45,70 |
| 72 | Sitework |
121 d | Wed 11/06/02 | Wed 04/23/03 | |
| 73 | North Lot |
15 d | Wed 11/20/02 | Tue 12/10/02 | |
| 74 | Demo/Fine Grade |
2 d | Wed 11/20/02 | Thu 11/21/02 | 15 |
| 75 | Utilities |
3 d | Fri 11/22/02 | Tue 11/26/02 | 74 |
| 76 | Irrig |
3 d | Fri 11/22/02 | Tue 11/26/02 | 74 |
| 77 | C/G/S |
5 d | Wed 11/27/02 | Tue 12/03/02 | 75 |
| 78 | AC/Grass Pave |
4 d | Wed 12/04/02 | Mon 12/09/02 | 77 |
| 79 | Misc Site Furn |
5 d | Wed 12/04/02 | Tue 12/10/02 | 77 |
| 80 | Planting |
5 d | Wed 12/04/02 | Tue 12/10/02 | 76,77 |
| 81 | Courtyard |
98 d | Wed 11/06/02 | Fri 03/21/03 | |
| 82 | Block Walls |
8 d | Wed 11/06/02 | Fri 11/15/02 | |
| 83 | Fine Grading |
2 d | Thu 02/20/03 | Fri 02/21/03 | 82,43,68 |
| 84 | Utilities |
5 d | Mon 02/24/03 | Fri 02/28/03 | 83 |
| 85 | Irrigation |
7 d | Mon 02/24/03 | Tue 03/04/03 | 83 |
| 86 | Cisterns |
5 d | Mon 03/03/03 | Fri 03/07/03 | 84 |
| 87 | Flatwork |
10 d | Mon 03/03/03 | Fri 03/14/03 | 84 |
| 88 | Misc Site Furn |
5 d | Mon 03/17/03 | Fri 03/21/03 | 86,87 |
| 89 | Planting |
5 d | Mon 03/17/03 | Fri 03/21/03 | 85,87 |
| 90 | SouthEast Lot |
20 d | Thu 02/20/03 | Wed 03/19/03 | |
| 91 | Demo/Fine Grade |
3 d | Thu 02/20/03 | Mon 02/24/03 | 43,68 |
| 92 | Utilities |
2 d | Tue 02/25/03 | Wed 02/26/03 | 91 |
| 93 | Irrig |
3 d | Tue 02/25/03 | Thu 02/27/03 | 91 |
| 94 | C/G/S |
5 d | Thu 02/27/03 | Wed 03/05/03 | 92 |
| 95 | AC/Grass Pave |
5 d | Thu 03/06/03 | Wed 03/12/03 | 94 |
| 96 | Misc Site Furn |
2 d | Thu 03/06/03 | Fri 03/07/03 | 94 |
| 97 | Planting |
5 d | Thu 03/13/03 | Wed 03/19/03 | 93,95 |
| 98 | SouthWest Lot |
40 d | Wed 11/06/02 | Tue 12/31/02 | |
| 99 | Haul-off Spoils |
3 d | Wed 11/06/02 | Fri 11/08/02 | |
| 100 | Demo/Fine Grade |
3 d | Mon 11/11/02 | Wed 11/13/02 | 99 |
| 101 | Utilities |
7 d | Thu 11/14/02 | Fri 11/22/02 | 100 |
| 102 | Irrig |
5 d | Thu 11/14/02 | Wed 11/20/02 | 100 |
| 103 | Walls/Stairs |
10 d | Mon 11/25/02 | Fri 12/06/02 | 101 |
| 104 | C/G/S |
10 d | Mon 12/09/02 | Fri 12/20/02 | 103 |
| 105 | AC/Grass Pave |
2 d | Mon 12/23/02 | Tue 12/24/02 | 104 |
| 106 | Misc Site Furn |
5 d | Mon 12/23/02 | Fri 12/27/02 | 104 |
| 107 | Planting |
5 d | Wed 12/25/02 | Tue 12/31/02 | 102,105 |
| 108 | Shade Structure |
35 d | Thu 02/20/03 | Wed 04/09/03 | |
| 109 | Drill Holes |
5 d | Thu 02/20/03 | Wed 02/26/03 | 43,68 |
| 110 | Set Posts |
5 d | Thu 02/27/03 | Wed 03/05/03 | 109 |
| 111 | Hardware |
10 d | Thu 03/06/03 | Wed 03/19/03 | 110 |
| 112 | Trellises |
10 d | Thu 03/06/03 | Wed 03/19/03 | 110 |
| 113 | Paint Poles |
5 d | Thu 03/06/03 | Wed 03/12/03 | 110 |
| 114 | Paint Hdwe/Trellises |
5 d | Thu 03/20/03 | Wed 03/26/03 | 111,112 |
| 115 | Fabric/Mesh |
10 d | Thu 03/27/03 | Wed 04/09/03 | 113,114 |
| 116 | Site Punchlist |
10 d | Thu 04/10/03 | Wed 04/23/03 | 115,78,79,80,88,89,96,97,106,107 |
| 117 | Completion |
0 d | Wed 11/06/02 | Wed 11/06/02 |