Casa Nueva Office
Building
Wednesday, March 26, 2003
Roof Deck, Windows, Rough Plastering and Interior Wall Framing... |
 |
 |

Interior Space (left) -- Main Lobby & Stair (right)
Main Fire Sprinkler System Control (left) -- Pipe Cutting
Device (right) |
| |
Elevator Rail Installation |
| |
A lot of pipes, conduit and wiring
(here is a typical electrical, phone and data configuration) |
| |

Drywall Installation (left) -- Plastering (mid) -- Electrical
(right) |
| |

Plaster Screeds and mesh -- At Window (left) -- At Concrete
(mid) -- At Cornice (right) |
| |

More Screeds and trims -- Corners (top 3) --
Expansion Joint (lower left) -- Profiles (bottom right) |
| |

Gravel goes on the roof (photo bottom shows wet tar) |
| |

Flashing Pitch Pocket (left) -- Oozing Tar and gravel... |
| |

Poring the tar and sprinkling the gravel (2 inches of gravel
over 1/2" of tar) |
| |

The Fire Sprinkler, Drywaller and Elevator workmen all in
this small area.
The Fire Sprinkler lines where placed a few months
ago, but extended down past the ceiling line, which is typical. When the
ceiling framing is placed, then the fire lines are trimmed to fit the actual
ceiling placement. |
| |

Looking across the courtyard and roof. |
| |

Panorama |