Formwork...Steel...Plumbing...

Up In The Cage...Down In The Ground.

Two steel workers installing horizontal rebars.

 
  Oak Tree...hang in there!

Vertical shear walls as viewed from the parking lot below.

   
Elevator pit...Large Retaining Wall

(left) Brian worked on the formwork for the elevator pit...other crew members work on the steel for the retaining wall...you can see tow up on the cage.

Overview and Detail
The formwork assembly is like a sandwich...one half of the sandwich (right) has been placed.

 

 

Formwork
Forms in the process of vertical placement.

 

 
Large Retaining Wall Formwork

Joe and Yvonne are constructing the formwork for the retaining wall...no small task.


Vertical Formwork Attachment

A bolt in the concrete holds the vertical formwork in place.

Plumbing and Shear Walls
(left) plumbing and rebar await the slab...(right) two shear wall forms are up...

   
Panorama View
 
   

Another view of formwork
Vertical shear walls are in the air...the large retaining wall goes up, just to the left.