![]() Office of the County Architect |
Casa Nueva Office
Building Wednesday, June 17, 2002 Formwork...Steel...Plumbing...Concrete Pour |
|
|
|
|
Vertical Form Work The vertical form work was assembled on the ground (see June 5th) first, then set in-place by crane. Each panel is then leveled with plastic shims and locked in-place with wing bolts. |
![]() Vertical Wall Assembly nears completion. The vertical shear walls are reinforced concrete. They are constructed using a "sandwich" assembly of forms. Here the second half is being installed.
|
||
|
Brad (left) and his supervisor Rob! There is hundreds of feet of conduit for electrical and communications and that is just in the concrete foundation and slab. |
||
Yvonne is at the top of the photo and her helpers below...the tricky assembly of the wall concrete forms takes time. |
||
|
Yvonne is on top of the wall framing to the right and Joe is on the steel cage at mid-photo. They and their helpers are assembling the concrete form work. |
||
![]()
Brad working with electrical conduit. |
||
|
Formwork |
||
Large Retaining Wall Formwork Joe and Yvonne are constructing the formwork for the retaining wall...no small task. |
||
The (left) photo is the view from the San Antonio Building parking lot. The elevator enclosure is the large wood form in the middle of the photo. Another concrete truck arrives and deposits its load in the pumper truck. |
||
![]()
Keeping History |
||
![]() Panorama View |
||
|
Pumper Truck... |
||
![]()
Concrete Goes In! |
||
|
|
|
|
|
|
||