![]() Office of the County Architect |
Casa Nueva Office
Building Wednesday, July 3, 2002 Formwork...Steel...Concrete Pour |
|
|
|
|
Slab Form Work (left) communications conduit on its way to the San Antonio Building...(right) slab form work ready. |
Before...After (left) Steel ready for concrete...(right) Same spot after concrete...
|
||
|
Keeping the earth moving... Excess earth from footings is stock piled...then moved. |
||
|
||
|
(left) Architect and Contractor...(middle & right) Yianni [architect] and Kathy [main tenant-APCD] review the work progress. |
||
Concrete in the wall.... |
||
![]() Concrete
going into the wall. |
||
Next Steel Cage Ready... This steel cage will be installed at the top of the concrete walls (shown here). |
||
A worker taps the plywood to insure there are no air
pockets... Formwork for the concrete slab going in... |
||
Surgio working on
slab formwork! |
||
![]() Electrical and Communication Conduits ready for concrete... |
||
|
Another View... |
||
![]() Panorama |
||
The mountain stockpile is leaving the site...we are all happy about that! |
||
|
|
|
|
|
|
||