Casa Nueva Office Building
Wednesday, August 7, 2002

Next Retaining Wall Begins, Under Slab Work Completes...

 

Second Floor Shear Walls...formwork ready to come down.

Here you can see the waterproofing along the back side of the large retaining wall....oops, something to fix.

 

 

Second Retaining wall footing formwork goes in..

Another shot...

 

 

Tie-In with large retaining wall

 

 



From the footing formwork to the top of slope is 12 feet.

 (left) Sample detail wall (right) Anchor bolt form holder

    
Under slab work continues...vapor barrier goes in

   



 

 

 

 

 

 

 

 

 

 

Next retaining wall being laid out...

 
Panorama