Casa Nueva Office
Building Wednesday, September 11, 2002 Next Retaining Wall Continues, Steel Work Begins... |
![]() |
|
| America Remembers Presentation | |||
|
|
|
Steel prep work... Two actions are executed on these cross beams...one certain cross beams, the top and bottom flanges are removed to allow the beam to fit the adjacent beam....then anchor bolt studs are "arc-welded" at regular intervals for the floor or roof deck attachment. In the picture to the right above, you can see the burst of the arc as the stud is attached. We will hear more about the steel workers next week.
Steel worker prepares bolting stud on steel cross beams. Each bolt stud is "arc-welded" to the steel flange. |
|
|
Our mountain continues to move...one loader scoop at a time.
|
|||
|
Forest of steel columns... |
|||
|
Final preparations to second retaining wall before concrete arrives. |
|||
Entry
door mat holder is ready for the next concrete pour. This mat feature is
part of the LEEDs rating for indoor
air quality.
![]() |
|||
![]() ![]()
First section of vertical columns have been installed, cross beams are next. |
|||
![]() |
Steel column base bolts to concrete foundation. Additional lateral force transfer flanges have been installed on some of these columns. | ||
![]() A forest of columns... |
|||
|
|
|||
|
|
|||
|
|
|||