Construction |
Construction Photographs Main Page This page will continue to change as the building takes shape. Below you will see a number of links, more added as I visit the project. Last Updated on: Monday September 01, 2003 Allow time for pictures to download... Page with panorama over time.
Short Clips
About The Workers Construction Schedule
|
|||||
| January 30, 2002 | Pre-Demolition of old Casa Nueva Building | |||||
| February 4 2002 | Fire Department Training...remains. | |||||
| March 19, 2002 | Removing Vegetation... | |||||
| April 1, 2002 | Demolition of original Casa Nueva Begins. | |||||
| April 3, 2002 | Rough Grading for new building | |||||
| April 17, 2002 | Grading Continues | |||||
| April 24, 2002 | Site Compaction Underway | |||||
| May 1, 2002 | Site Compaction Continues | |||||
| May 8, 2002 | Finish Building Pad Is Ready. | |||||
| May 15, 2002 | Footing Excavation | |||||
| May 22, 2002 | Footing Steel Work continues | |||||
| May 31, 2002 | Second pour of concrete | |||||
| June 5, 2002 | Third pour of concrete, formwork and plumbing | |||||
| June 7, 2002 | Elevator pit, vertical shear wall formwork and plumbing | |||||
| June 12, 2002 | Elevator pit, vertical shear wall formwork and plumbing...continue | |||||
| June 17, 2002 | Concrete Pour of Vertical Shear Walls | |||||
| June 26, 2002 | Concrete Pour of Vertical Shear Walls and short stem footing | |||||
|
|
July 3, 2002 | Concrete Pour of retaining wall and formwork for slab | ||||
| July 10, 2002 | Formwork on large retaining wall comes down... | |||||
| July 17, 2002 | Formwork for second floor shear walls goes up... | |||||
| July 24, 2002 | Excavation for retaining wall two has begun... | |||||
| July 31, 2002 | Under slab electrical and plumbing has begun... | |||||
| August 7, 2002 | Main Concrete Slab Prep | |||||
| August 14, 2002 | Main Concrete Slab Pour... | |||||
| August 21, 2002 | Second Retaining Wall Formwork and Steel Columns Arrive. | |||||
| August 28, 2002 | Detail work continues on second retaining wall...slab depressions poured. | |||||
| September 4, 2002 | No Update | |||||
![]() America Remembers |
Second retaining wall and steel column work begins. | |||||
| September 18, 2002 | Utility Trenching picks up again, steel beam prep continues. | |||||
| September 25, 2002 | Steel Floor Beams Installed--Formwork Off Decorative Wall | |||||
| October 2, 2002 | Steel Floor Beams Installation continues | |||||
| October 9th and 16th. | No Updates | |||||
| October 23, 2002 | Steel Floor Beams Installation continues | |||||
| October 30, 2002 | Steel Floor Beams Installation continues...Courtyard ramp walls begin | |||||
| November 6, 2002 | No Update | |||||
| November 13, 2002 | Steel Beams continue...Floor Trusses begin | |||||
| November 20, 2002 | Steel Beams continue...Floor Deck begins | |||||
| November 27, 2002 | Floor Deck Continues... | |||||
| December 4, 2002 | Floor Deck Continues...HVAC Begins... | |||||
| December 11, 2002 | Floor Deck Continues...HVAC continues...Fire Sprinklers Begins... | |||||
| December 18, 2002 | Floor Deck Continues...Steel Continues...Fire Sprinklers Continue... | |||||
![]() December 24, 2002 |
Steel flying for
roof supports...Metal Studs...Electrical... Happy Holidays Everyone! |
|||||
| January 1, 2003 | No Update | |||||
| January 9, 2003 | Roof trusses | |||||
| January 15, 2003 | No Update | |||||
| January 22, 2003 | Roof trusses and interior walls continue | |||||
| January 29, 2003 | Roof deck going in...interior walls continue... | |||||
| February 5, 2003 | Skin underlayment begins, interior stairs go in... | |||||
| February 12, 2003 | No Update | |||||
| February 19, 2003 | Roof HVAC, Window & Doors Frames & skin underlayment | |||||
| February 26, 2003 | No Update | |||||
| March 5, 2003 | Site work, pre-roofing and interior work | |||||
| March 12, 2003 | No Update | |||||
| March 19, 2003 | Roofing, interior drywall and window & door frames | |||||
| March 26, 2003 | Roofing, interior drywall and window & door frames | |||||
| April 2, 2003 | No Update | |||||
| April 9, 2003 | Plastering, Tile Beds, Electrical, Network Wiring, ect.. | |||||
| April 16, 2003 | Ceramic Tile, Site Work, Plastering | |||||
| April 23, 2003 | Exterior Plaster Finishing, Interior Finishes Begin, Site Work Continues | |||||
| April 30, 2003 | Interior Finishes Continue, Site Work Continues | |||||
| May 7, 2003 | Interior Finishes Continue, Site Work Continues | |||||
| May 14, 2003 | Interior Finishes Continue, Site Work Continues | |||||
| May 21, 2003 | No Update | |||||
| May 28, 2003 | No Update | |||||
| June 4, 2003 | Interior Finishes Continue, Site Work Continues, Trellis Begins | |||||
| June 11, 2003 | No Update | |||||
| June 18, 2003 | Interior finishes, parking lots and trellis work continue | |||||
| June 25, 2003 | Interior finishes, parking lots and trellis work continue | |||||
| Clips About The Workers | Foundation/Shear Walls/Retaining Wall | |||||
| Yvonne (Edrow Engineering and Construction) | ||||||
| Brian (Edrow Engineering and Construction) | ||||||
| Joe (Edrow Engineering and Construction) | ||||||
| Rick (Carroll Construction's Superintendent) | ||||||
| Sergio (Edrow Engineering and Construction) | ||||||
| Steel Framing/Wall Framing | ||||||
| Aaron (Russ Jones Steel) | ||||||
Page updated on
Monday, September 01, 2003
Comments?
Remembrance Photo Gallery (FEMA.GOV)
» Small Images 1.8MB
(Download times: 4.5 min. over 56K / 8.73 min. over 28.8K)
» Large Images 2.68 MB
(Download time: 6.38 min. over 56K / 12.4 min. over 28.8K)
» HTML Version
»Download the Macromedia Plug-in