Casa Nueva Building

WebSite


News

Project Team

Architectural Drawings

Construction
September 01, 2003

Construction Photographs Main Page

This page will continue to change as the building takes shape. Below you will see a number of links, more added as I visit the project. 

Last Updated on: Monday September 01, 2003

Allow time for pictures to download...


Page with panorama over time.
Page loads slowly...be patient.

January, 2002 to June, 2002

July, 2002 to December 2002

January 2003 to September, 2003

 

Short Clips About The Workers
updated,  September 01, 2003


Construction Schedule

WEB Page or PDF


 

January 30, 2002 Pre-Demolition of old Casa Nueva Building
February 4 2002 Fire Department Training...remains.
March 19, 2002 Removing Vegetation...
April 1, 2002 Demolition of original Casa Nueva Begins.
April 3, 2002 Rough Grading for new building
April 17, 2002 Grading Continues
April 24, 2002 Site Compaction Underway
May 1, 2002 Site Compaction Continues
May 8, 2002 Finish Building Pad Is Ready.
May 15, 2002 Footing Excavation
May 22, 2002 Footing Steel Work continues
May 31, 2002 Second pour of concrete
June 5, 2002 Third pour of concrete, formwork and plumbing
June 7, 2002 Elevator pit, vertical shear wall formwork and plumbing
June 12, 2002 Elevator pit, vertical shear wall formwork and plumbing...continue
June 17, 2002 Concrete Pour of Vertical Shear Walls
June 26, 2002 Concrete Pour of Vertical Shear Walls and short stem footing

 
Happy 4th!

July 3, 2002 Concrete Pour of retaining wall and formwork for slab
July 10, 2002 Formwork on large retaining wall comes down...
July 17, 2002 Formwork for second floor shear walls goes up...
July 24, 2002 Excavation for retaining wall two has begun...
July 31, 2002 Under slab electrical and plumbing has begun...
August 7, 2002 Main Concrete Slab Prep
August 14, 2002 Main Concrete Slab Pour...
August 21, 2002 Second Retaining Wall Formwork and Steel Columns Arrive.
August 28, 2002 Detail work continues on second retaining wall...slab depressions poured.
September 4, 2002 No Update
Photo of New York fire worker taking a break amongst the debris of the World Trade Center. FEMA photo by Andrea Booher
America Remembers

September 11, 2002

Second retaining wall and steel column work begins.
September 18, 2002 Utility Trenching picks up again, steel beam prep continues.
September 25, 2002 Steel Floor Beams Installed--Formwork Off Decorative Wall
October 2, 2002 Steel Floor Beams Installation continues
October 9th and 16th. No Updates
October 23, 2002 Steel Floor Beams Installation continues
October 30, 2002 Steel Floor Beams Installation continues...Courtyard ramp walls begin
November 6, 2002 No Update
November 13, 2002 Steel Beams continue...Floor Trusses begin
November 20, 2002 Steel Beams continue...Floor Deck begins
November 27, 2002 Floor Deck Continues...
December 4, 2002 Floor Deck Continues...HVAC Begins...
December 11, 2002 Floor Deck Continues...HVAC continues...Fire Sprinklers Begins...
December 18, 2002 Floor Deck Continues...Steel Continues...Fire Sprinklers Continue...

December 24, 2002
Steel flying for roof supports...Metal Studs...Electrical...

Happy Holidays Everyone!

January 1, 2003 No Update
January 9, 2003 Roof trusses
January 15, 2003 No Update
January 22, 2003 Roof trusses and interior walls continue
January 29, 2003 Roof deck going in...interior walls continue...
February 5, 2003 Skin underlayment begins, interior stairs go in...
February 12, 2003 No Update
February 19, 2003 Roof HVAC, Window & Doors Frames & skin underlayment
February 26, 2003 No Update
March 5, 2003 Site work, pre-roofing and interior work
March 12, 2003 No Update
March 19, 2003 Roofing, interior drywall and window & door frames
March 26, 2003 Roofing, interior drywall and window & door frames
April 2, 2003 No Update
April 9, 2003 Plastering, Tile Beds, Electrical, Network Wiring, ect..
April 16, 2003 Ceramic Tile, Site Work, Plastering
April 23, 2003 Exterior Plaster Finishing, Interior Finishes Begin, Site Work Continues
April 30, 2003 Interior Finishes Continue, Site Work Continues
May 7, 2003 Interior Finishes Continue, Site Work Continues
May 14, 2003 Interior Finishes Continue, Site Work Continues
May 21, 2003 No Update
May 28, 2003 No Update
June 4, 2003 Interior Finishes Continue, Site Work Continues, Trellis Begins
June 11, 2003 No Update
June 18, 2003 Interior finishes, parking lots and trellis work continue
June 25, 2003 Interior finishes, parking lots and trellis work continue
   
   
Clips About The Workers Foundation/Shear Walls/Retaining Wall
Yvonne (Edrow Engineering and Construction)
Brian (Edrow Engineering and Construction)
Joe (Edrow Engineering and Construction)
Rick (Carroll Construction's Superintendent)
  Sergio (Edrow Engineering and Construction)
   
  Steel Framing/Wall Framing
  Aaron (Russ Jones Steel)
   
   

Click to return to Gruber House HomePage Page updated on Monday, September 01, 2003
Comments?

 

Remembrance Photo Gallery (FEMA.GOV)
» Small Images 1.8MB (Download times: 4.5 min. over 56K / 8.73 min. over 28.8K)
» Large Images 2.68 MB (Download time: 6.38 min. over 56K / 12.4 min. over 28.8K)
» HTML Version

 »Download the Macromedia Plug-in