January 2003 to September, 2003

Change Over Time
(this page takes a long time to load)

 

   

Jan 9th: Roof deck going on...

   


 

No project report on Jan 1st or Jan 15th

   


 

Jan 22nd: Remaining roof deck goes on...

 

   

Jan 29th: Exterior Wall Framing...Roof Deck

 
   

Feb 5th: Remaining roof deck goes on...Exterior Wall Framing

 
   

No project report on Feb 12th

 

   

Feb 19th: Exterior Skin...Roof

 

   

Feb 26th: No Report

   

March 5th: Roof Materials On-Site---Windows Go In---Site Work Begins

   

 

March 12th: No Report

 

   

March 19th: Roof Starts---Windows Go In---Site Work Continues---Interior Work Continues

   

 

March 26th: Roof Materials On-Site---Windows Go In---Site Work Continues

   

April 9th: Roof Materials On-Site---Windows Go In---Site Work Continues

No Report for April 2, 2003

   
 

April 16th: Roof Materials On-Site---Windows Go In---Site Work Continues

   
April 23rd: Exterior Plaster Near Completion---Windows Go In---Site Work Continues
   

April 30th: Interior Finishes Underway---Site Work Continues

   
May 7th: Exterior Plaster Near Completion---Windows Go In---Site Work Continues
   


 

May 14th: Exterior Plaster Near Completion---Windows Go In---Site Work Continues

   

May 21 & 28 No Update:

 

   

June 4th: Interior Painting Continues--Site Work Continues

   


June 18th: Interior Painting Continues--Site Work Continues


 

   


June 27th: Interior Painting Continues--Site Work Continues