Casa Nueva Office Building January 2003 to September, 2003 Change Over Time |
|
|
|
|
|
Jan 9th: Roof deck going on... |
||
|
No project report on Jan 1st or Jan 15th |
||
|
Jan 22nd: Remaining roof deck goes on...
|
||
|
Jan 29th: Exterior Wall Framing...Roof Deck |
||
|
Feb 5th: Remaining roof deck goes on...Exterior Wall Framing |
||
|
No project report on Feb 12th
|
||
|
Feb 19th: Exterior Skin...Roof
|
||
Feb 26th: No Report |
||
|
March 5th: Roof Materials On-Site---Windows Go In---Site Work Begins |
||
|
March 12th: No Report
|
||
|
March 19th: Roof Starts---Windows Go In---Site Work Continues---Interior Work Continues |
||
March 26th: Roof Materials On-Site---Windows Go In---Site Work Continues |
||
April 9th: Roof Materials On-Site---Windows Go In---Site Work Continues No Report for April 2, 2003 |
||
|
April 16th: Roof Materials On-Site---Windows Go In---Site Work Continues |
||
![]() April 23rd: Exterior Plaster Near Completion---Windows Go In---Site Work Continues |
||
![]() April 30th: Interior Finishes Underway---Site Work Continues |
||
![]() May 7th: Exterior Plaster Near Completion---Windows Go In---Site Work Continues |
||
May 14th: Exterior Plaster Near Completion---Windows Go In---Site Work Continues |
||
|
May 21 & 28 No Update:
|
||
![]() June 4th: Interior Painting Continues--Site Work Continues |
||
|
|
||
|
|
||
|
|
|
|
|
|
||